Contract opportunity

Central Utility Building Addition and Renovation Construction, UIP Subproject 1-CUB

Solicitation from Department of Energy.

Data as of Oct 24, 2026. Sources: SAM.gov and Grants.gov. Snapshot govcon-directory-20261024T104923Z-2151694.

This product uses the Grants.gov API but is not endorsed or certified by the U.S. Department of Health and Human Services. Counts and totals are computed by DSE from public SAM.gov and Grants.gov notices. Text from Grants.gov may be shortened or have contact details removed. The original notice on Grants.gov is the authoritative version.

Closing in 24 days

Notice details

Agency
Department of Energy
Sub-tier agency
ENERGY, DEPARTMENT OF
Notice type
Solicitation
Solicitation number
RFP-376508-CD
NAICS
236210 Industrial Building Construction
Product/service code
Z2EZ
Place of performance
Batavia, Illinois
Posted
Oct 8, 2026
Response deadline
Nov 17, 2026
Source
SAM.gov

Description

On October 7, 2026, Amendment No. 2 was issued to correct badge access link provided in Amendment No. 1. On October 6, 2026, Amendment No. 1 was issued to provide dates for site visits. This scope of work is to build an addition and renovate the Central Utility Building (CUB). The CUB supplies chilled water, hot water, low conductivity water, and makeup water to various lab buildings and systems. These systems serve both comfort cooling and heating needs, as well as process cooling and utility requirements. It is vital to Fermilab�s mission that CUB be revitalized and expanded, ensuring the ability to serve existing and future loads. The General contractor shall furnish all required supervision, labor, materials, tools, plant and appurtenances necessary to perform diligently and fully all work as described in the drawings and technical specifications. All work includes transportation, overhead, bonding costs, safety oversight, quality control oversight, and supervision as required to construct the project described in the drawings, technical specification and the detailed description contained herein. The critical schedule constraint for construction of this project is Fermilab�s accelerator shutdown, with an anticipated scheduled start on January 1, 2028, and anticipated end date of January 1, 2030- these dates may change depending on the needs of the Lab. The General Contractor must start their on-site efforts, and complete the construction scope under this contract

Summarized from the official notice. The description is shortened; read the full text on the official notice.

Official notice

View on SAM.gov →

Requirements and amendments are controlled by the official notice.

DSE verdict

The DSE fit verdict for this notice is available to DSE GovCon subscribers. It is not published on this page.

See DSE GovCon plans →

Similar open notices

  1. Construction Contract Sources SoughtClosing in 5 daysENERGY, DEPARTMENT OF · Posted Sep 24, 2026 · Closes Oct 29, 2026

Get free alerts

Email alerts for notices like this one are free on DSE GovCon Intelligence.

Set up free alerts →

Frequently asked questions

When is the response deadline?

The published deadline is Nov 17, 2026. That is 24 days after the data date.

What NAICS code applies?

NAICS 236210, Industrial Building Construction.

Which agency issued this notice?

Department of Energy.

Where is the official notice?

The link under Official notice opens the source listing.